Avon Lake, Costs of Avon Lake deer cull less than expected May 7, 2015 Ohio

Ohio Urban Deer Management News and Information Archive



Avon Lake, Costs of Avon Lake deer cull less than expected May 7, 2015 Ohio, The Chronicle-Telegram
... an initial service agreement with the USDA to spend up to $15,960 for sharpshooting services, but the actual cost came in at $8,557 for the 19 deer that were killed ...  more than $450 per deer ... A total of 696 pounds of venison was donated ... roughly $12 per pound...


These articles have been reviewed for relevance and content.  Some links to the original article may no longer be active.